|
Trans-Alaska
Pipeline
The
800-mile-long Trans Alaska Pipeline System (TAPS) is one of the largest pipeline
systems in the world. It stretches from Prudhoe Bay on Alaskas North Slope,
through rugged and beautiful terrain, to Valdez, the northernmost ice-free port
in North America. All of the oil is transported to refineries in the United
States.
The concept of transporting oil
south from Alaska was discussed as early as the 1960s. In 1968, large crude oil
reserves were discovered at Prudhoe Bay by the Atlantic Richfield Company
(ARCO). ARCO joined with BP Oil and Humble Oil to form the Trans-Alaska Pipeline
Systems (TAPS). TAPS was proposed to ship crude oil to the southern Alaska
seaport of Valdez (an ice-free port), from where it would be shipped to
refineries by tanker.
Pipeline construction from
Prudhoe Bay required transiting a route where much of the right-of-way was on
federal and state lands. Legislation (the Trans-Alaska Pipeline Authorization
Act [P.L. 93-153]) was required to end what had become a stalemate over the
route. This right-of-way legislation enabled the pipeline to be constructed.
Environmental studies for the
pipeline were started and applications for permits submitted in 1968. Suits were
filed by environmental groups and others to block pipeline construction in 1970.
Several Native villages filed a lawsuit claiming the pipeline would cross their
land. The land ownership question was settled with Congressional passage of the
Alaska Native Land Claims Settlement Act and its signature into law by President
Richard Nixon in December 1971.
The 48-inch special cold-weather
steel was ordered from Japan in April 1969. The building permit for the pipeline
was issued in 1974.
Valdez
Marine Terminal
The pipeline route
would cover 800 miles from Prudhoe Bay to the port of Valdez, the northernmost
ice-free port in the United States.
Actual construction began in
April 1974 and was completed in June 1977 at a cost of approximately $8 billion.
At the time, it was the largest privately funded construction project in
history. Approximately 2,000 contractors and subcontractors, as well as
approximately 70,000 workers, were employed to work on the project.
Paralleling the pipeline from
Livengood to Deadhorse, the Dalton Highway (locally known as the Haul Road) was
built as a supply route for use in construction, operation, and maintenance of
the northern portion of TAPS and the oil fields on the North Slope. This road is
now a State highway.
Valdez
Marine Terminal
The
Alyeska Pipeline Service Company, named after the Aleut word Alyeska meaning
mainland, was established in 1970 and charged with designing, constructing,
operating, and maintaining the Trans Alaska Pipeline System, commonly called
TAPS.
Key events in the
history of the Trans-Alaska Pipeline System
| Date |
Event |
|
March 1968
|
Oil
discovered at Prudhoe Bay |
|
August 14, 1970
|
Alyeska
Pipeline Service Company incorporated by the owner companies |
|
March, 1972
|
Department
of Interior issues final environmental impact statement for TAPS |
|
November 16, 1973
|
Trans-Alaska
Pipeline Authorization Act signed into law |
|
January 23, 1974
|
Federal
Agreement and Grant of Right-of-Way |
|
May 3, 1974
|
State Lease |
|
April 29, 1974
|
Haul Road
construction begins |
|
September 29, 1974
|
Haul Road
construction completed |
|
May 27, 1975
|
First pipe
laid (Tonsina River) |
|
October 11, 1975
|
Yukon River
bridge completed |
|
May 31, 1977
|
Final
pipeline weld |
|
June 20, 1977
|
First oil
flows from Pump Station 1 |
|
July 28, 1977
|
First oil
reached VMT |
|
August 1, 1977
|
First
oil-laden tanker (ARCO Juneau) leaves Valdez Marine Terminal |
|
July 1, 1979
|
Drag
reducing agent first used |
|
1988
|
Peak average
daily throughput of 2.03 million bbl/day |
|
March 24, 1989
|
Exxon Valdez
oil spill |
|
July 10, 1989
|
Alyeska Ship
Escort/Response Vessel System established |
|
1990
|
Federal Oil
Pollution Act of 1990 |
|
1990
|
Joint
Pipeline Office established |
|
1990
|
Prince
William Sound Regional Citizens Advisory Council contract signed with
Alyeska |
|
1990
|
HB 567
enacted by Alaska Legislature amending oil pollution laws |
|
1991
|
Atigun
reroute |
|
1993
|
Congressional
hearings on TAPS operations |
|
March 5, 1994
|
10 billionth
bbl reaches VMT |
|
1996 - 1997
|
Pump
Stations 2, 6, 8, and 10 taken off-line and placed on standby due to
lower throughput |
|
1997
|
Tanker vapor
recovery system added at VMT |
|
August 12, 1997
|
15,000th
tanker leaves VMT |
|
April 27, 2000
|
13 billionth
barrel reaches VMT |
- The Trans-Alaska Pipeline
System was designed and constructed to move oil from the North Slope of
Alaska to the northern most ice- free port- Valdez, Alaska.
- Length: 800 miles.
- Diameter: 48 inches.
- Crosses three mountain ranges
and over 800 rivers and streams.
- Cost to build: $8 billion in
1977, largest privately funded construction project at that time.
- Construction began on March
27, 1975 and was completed on May 31, 1977.
- First oil moved through the
pipeline on June 20, 1977.
- Over 14
billion barrels have moved through the Trans Alaska Pipeline System.
- First tanker to carry crude
oil from Valdez: ARCO Juneau, August 1, 1977.
- Tankers loaded at Valdez:
16,781 through March 2001.
- Storage tanks in Valdez- 18
with total storage capacity of 9.1 million barrels total.
Gulkana
River tiered-arch bridge
The
consortium of companies that own TAPS today includes:
BP Pipelines (Alaska) Inc. 46.93%
ConocoPhillips Transportation Alaska, Inc. 28.29%
ExxonMobil Pipeline Company, 20.34%
Unocal Pipeline Company, 1.36%
Koch Alaska Pipeline Company, L.L.C., 3.08%

Pipeline
Operations

Operators
at the Valdez Operations Control Center monitor the performance of pipeline
operations
- Maximum daily throughput
2.136 million bbl., avg.
(With 11 pump stations operating). Rates exceeding 1,440,000 bbl./day assume
drag reduction agent (DRA) injection.
- Maximum daily throughput
2000 (with 7 pump stations operating) .99 million bbl., avg. Rates
exceeding 1,000,000 bbl./day assume DRA injection
- Fuel required for all
operations (fuel oil equivalent) 210,000 gal/day (also see fuel
requirements under Pump Stations, and Marine Terminal).
- Pressure
- Design, maximum 1,180
psi
- Operating, maximum
1,180 psi
- Pump Station facilities in
original design 12 pump stations with 4 pumps each.
- Pump Stations operating, Nov.
1, 1998 7: PS 1, 3, 4, 5, 7, 9, 12. PS 5 is a relief station only.
PS 11 is a security site. PS 8 placed in standby June 30, 1996.
PS 10 placed in standby July 1, 1996. PS 2 placed in standby July 1,
1997. PS 6 placed in standby August 8, 1997.

Pipeline
Engineering

Cost
Approximately $8 billion for
construction of entire system, including Terminal and pump stations, at
conclusion of initial construction period in 1977. Does not include interest on
capital investment, or capital construction after 1977.

Concrete weights
- Pipe coating, river crossings
75,000 lbs. per 40-ft. section
- Saddles, flood plains
18,500 lbs. each
Mainline crossings
- Animal, elevated, minimum
height 10 ft.
- Animal, elevated, number
554
- Animal, buried, number 23
- Animal, buried, refrigerated,
location MP 645 and MP 649
- Bridges
- Pipeline, types and number
- Orthotropic box girder
1
- Plate girder 9
- Suspension 2
- Tied arch 1
- Total 13
- Road, number
- North of Yukon 21
- South of Yukon 23
- Road crossings,
refrigerated Glenn Highway at Glennallen

Design modes
Selection Soil sampling and
other means were used to determine soil types along the route. Where thaw-stable
soils were found, the pipeline was buried in the conventional manner. In areas
of thaw-unstable soils, and where heat from the oil in the pipeline might cause
thawing and consequent loss of soil foundation stability, the pipeline was
insulated and elevated above ground by means of a unique support system.
Basic types and miles of each
- Above-ground 420 mi.
- Conventional below-ground
376 mi.
- Refrigerated below-ground
4 mi.
Description
- Above-ground
Specially designed vertical supports were placed in drilled holes or driven
into the ground. In warm permafrost and other areas where heat might cause
undesirable thawing, the supports contain two each, 2-inch pipes called
"heat pipes," containing anhydrous ammonia, which vaporizes below
ground, rises and condenses above-ground, removing ground heat whenever the
ground temperature exceeds the temperature of the air. Heat is transferred
through the walls of the heat pipes to aluminum radiators atop the pipes.
- Conventional below-ground
The pipe is underlain with a layer of fine bedding material and covered with
prepared gravel padding and soil fill material, in a ditch from 8 ft. to 16
ft. deep in most locations, but up to 49 ft. deep at one location. Zinc
ribbons, which serve as sacrificial anodes to inhibit corrosion of the pipe,
are buried alongside the pipeline. The Atigun pipe replacement section, 8.5
miles in length, has four magnesium ribbon sacrificial anodes installed.
Electrical currents in the earth's surface, called "telluric
currents" and caused by the same phenomenon that generates the Northern
Lights, can be picked up by the pipeline and zinc anodes. The zinc anodes
act like grounding rods to safely return these currents back to the earth,
reducing the risk of damage to the pipeline.
- Special burial,
non-refrigerated In areas of thaw-unstable soils calling for
elevated pipeline construction, but where the pipeline had to be buried for
highway, animal crossings, or avoidance of rockslides and avalanches, the
line was insulated, to protect the permafrost from the heat of the pipeline,
and buried.
- Special burial,
refrigerated In some areas the line was insulated and buried in a
refrigerated ditch. Refrigeration plants at each of these points circulate
chilled brine through loops of 6 inch diameter pipe to maintain the soil in
a stable frozen condition.
Pipeline buried in
the standard method lies on a layer of bedding material (well drained sandy
gravel without sharp rocks) covered with prepared gravel padding and soil fill
material.
Insulation
- Elevated pipeline,
thickness-3.75 in.
- Refrigerated below-ground
pipeline, thickness-3.2 in.
- Under gravel workpad or road-2
in. to 4 in. (limited areas only)

Tanana
River suspension bridge
Gabion & concrete mats
Used in Atigun Floodplain Pipe
Replacement Project for scour protection of the new pipe because less cover on
top of new pipe.
- Gabion mats, used 31,750 ft.
- Concrete mats, used 9,525 ft.
Land Ownership
Ownership, entire system, by
area:
- Federal government-6.27 sq.
mi. approx.
- State government-7.79 sq. mi.
approx.
- Private-1.33 sq. mi.
- Owner companies-2.9 sq. mi.
- Total area-19.29 sq. mi.
Ownership, pipeline only, length
- Federal government- 376 mi.
approx.
- State government-344 mi.
approx.
- Private-80 mi. approx.
(including 51 mi., Alaska Native Corp. land)
- Total 800 mi.
Pipeline in municipal
jurisdiction, approx.
- Arctic North Slope Borough -
179.2 mi.
- Fairbanks North Star Borough -
89.1 mi.
- City of Delta Junction - 5.5
mi.
- City of Valdez - 20.8 mi.
Linefill
Definition - Amount of oil in
pipeline from PS 1 to Marine terminal.
The linefill is 9,059,057 bbl.

Pump
Station 1 receives and meters oil from the producers
Permanent facilities
Access roads, dimensions 120
ft. to 7.5 mi. long; 28 ft. wide, minimum 3 ft. gravel base.
Access roads, number 225,
linking state roads with pipeline, pump stations and airfields.
Airfields, land status and length
- Federal land subject to and
operated under state leases
- Galbraith Lake 5,200
ft.
- Prospect 5,000 ft.
Pressure Relief Station 1 (PS
5, reinjects oil drained down for pressure relief, but does not have mainline
pumps and does not boost total stream).
Marine terminal 1 (Valdez).
Pig launching/receiving
facilities 3 (PS 1, 4, and Marine Terminal).
Pipe shoes, number 39,000
approx.
Pump stations, operating 11
(10 pump stations, 1 relief station)
Topping units 3 (PS 6, 8, and
10. PS 8 and 10 topping units placed in standby, summer 1996. PS6
topping unit placed in standby summer 1997.)
Pipeline Valves, types and number
- Check 81
- Gate 71
- Block 24
- Ball 1
- Total 177

Pump
Station 7 is about 1.3 miles southeast of the Tatalina River in a wooded area.
PS 7 is similar to PS 2 with two mainline pumps instead of three.
Thermal expansion
Definitions -
Thermal expansion - change in
pipe length due to change in crude oil temperature
Tie-in temperature - actual pipe
temperatures at the time when final welds were made which joined strings of pipe
into a continuous line
Hot position - pipe at maximum
oil temperature (145° F)
Cold position - pipe at minimum
steel temperature
(-60° F) (pre-startup)
Each 40 ft. length of pipe
expands .031 inches with each 10° F rise in temperature and contracts the same
distance with each 10°F drop in temperature.
Longitudinal expansion of typical
720 ft. straight above-ground segment from min. tie-in temperature to maximum
operating temperature - 9 inches.
Note: due to anchoring, the
pipeline does not expand lengthwise but shifts laterally on the above-ground
supports (See zig zag configuration , below)
Maximum above-ground lateral
movement-
- Tie-in to hot position - 8 ft.
- Tie-in to cold position - 4
ft.
Thermal stress - maximum, 25,000
psi - where below ground pipeline is fully restrained by the soil, the maximum
longitudinal stress due to change in temperature from pipe temperature at tie-in
to maximum oil temperature
Zig zag Configuration
Above-ground sections of the
pipeline are built in a zig zag configuration to allow for expansion or
contraction of the pipe because of temperature changes. The design also allows
for pipeline movement caused by an earthquake.
Refrigerated Burial of
Pipe

VSMs (Vertical Support
Members)
Basic data
- Number 78,000
- Diameter 18 in.
- Types 16, to accommodate
variety of soil and permafrost conditions.
Depth at which embedded 15
ft. to 70 ft.
Distance between
- Anchor supports 800 ft. to
1,800 ft.
- Standard supports 60 ft.
approx.
Heat pipes, number fitted with
61,000 (122,000 individual heat pipes, 2 per VSM, where fitted)

credit: Alyeska Pipeline Service
Company, State of Alaska, U.S. Department of the Interior Bureau of Land
Management
|